Top Movers

Company Announcements

Q4 and full year 2014 production results

Related Companies

RNS Number : 4650D
Polymetal International PLC
29 January 2015
 



 

 

Release time

 

IMMEDIATE

Date

29 January 2015

 

 

Polymetal International plc

Q4 and full year 2014 production results

 

Polymetal International plc (LSE, MOEX: POLY, ADR: AUCOY) (together with its subsidiaries - "Polymetal", the "Company", or the "Group") is pleased to announce the Group's production results for the fourth quarter and twelve months ended December 31, 2014.

HIGHLIGHTS

·     In 2014 Polymetal increased its gold equivalent ("GE") production by 12% to 1.43 Moz and exceeded both its original production guidance of 1.3 Moz of GE by 10% and the updated production guidance of 1.365 Moz by 5%. This achievement was mostly driven by the full ramp-up of Mayskoye and strong operational delivery at Dukat and Omolon.

·     Annual gold production for the year increased by 17% to 945 Koz. Annual silver production increased by 5% to 28.7 Moz. The share of gold in revenue composition increased to 69% compared to 63% in 2013.

·     On 23 January 2015 the Company paid a special dividend of US$ 0.20 per share, representing approximately US$ 84 million, which brings total dividends paid for the previous twelve months to US$ 0.36 per share, or US$ 149 million (representing an annual dividend yield of 3.9%1).

·     Net debt at 31 December 2014 decreased by US$ 83 million compared to 30 September 2014 to US$ 1,249 million (this figure already includes the liability for special dividend payable) as the Company continued to generate free cash flow driven by of strong operating and cost performance.

·     Polymetal continues to benefit from the depreciation of the Russian rouble against the US dollar. The Company reaffirms its full-year Total Cash Cost ("TCC) guidance of US$ 625-675 per GE oz, and expects All-in Sustaining Cash Cost ("AISC") of US$ 900-950 per GE oz.

·     The Company reiterates its production guidance of 1.35 Moz of GE for 2015 and 2016. In 2015, Polymetal expects a lower TCC of US$ 575-625 per GE oz and AISC of US$ 750-800 per GE oz. Capital expenditure in 2015 is expected to total approximately US$ 240 million (including exploration, capitalised stripping and spending on the Kyzyl project). This guidance is heavily dependent on the RUB/USD exchange rate, inflation in Russia, and oil price dynamics and is based on management's current estimates of these variables in 2015.

"In 2014 Polymetal materially exceeded its production guidance for the third consecutive year despite a challenging market environment. Over the last several years, Polymetal has continued to consistently deliver value to shareholders through substantial dividend payments", said Vitaly Nesis, the Group CEO, commenting on the results. "We are confident in our outlook for 2015 and intend to continue dividend payments in the current market environment."

___________________

(1)   For the last twelve months ended January 23, 2015. Dividend yield is calculated as dividends paid during the period divided by average share price.


3 months ended Dec 31,

% change1

12 months ended Dec 31,

% change1


2014

2013

2014

2013








Waste mined, Kt

17,665

21,028

-16%

77,458

84,956

-9%

Underground development, m

15,832

14,694

+8%

61,417

56,258

+9%

Ore mined, Kt

3,693

2,581

+43%

13,706

10,376

+32%

Open-pit

2,973

1,983

+50%

11,046

7,975

+39%

Underground

720

598

+20%

2,660

2,404

+11%

Ore processed, Kt

2,771

2,728

+2%

11,300

10,749

+5%

Production







Gold, Koz

299

212

+41%

945

805

+17%

Silver, Moz

5.5

5.7

-3%

28.7

27.2

+5%

Copper, tonnes

-

749

-100%

1,631

4,841

-66%

Gold equivalent, Koz2

391

310

+26%

1,431

1,282

+12%

Sales







Gold, Koz

337

268

+26%

943

818

+15%

Silver, Moz

8.1

7.8

+4%

29.3

27.4

+7%

Copper, tonnes

729

1,204

-39%

1,029

6,165

-83%

Revenue, US$m3

513

492

+4%

1,689

1,715

-2%








Net debt4

1,249

1,332

-6%

1,249

1,045

+20%








Safety5







LTIFR

0.70

1.20

-42%

0.65

0.59

+10%

FIFR

-

0.24

-100%

0.18

0.06

+200%

Notes:     (1) % changes can be different from zero even when absolute numbers are unchanged because of rounding. Likewise, % changes can be equal to zero when absolute numbers differ due to the same reason. This note applies to all tables in this release.

                (2) Based on 1:60 Ag/Au and 5:1 Cu/Au conversion ratios.

                (3) Calculated based on the unaudited consolidated management accounts. Concentrate sales are recorded based on forward prices for the expected dates of final settlement and concentrate revenue is presented net of refining and treatment charges.

(4) Non-IFRS measure, based on unaudited consolidated management accounts. Net debt equals to current and non-current borrowings less cash and cash equivalents. Comparative information is presented for 30 June 2014 (for the three months period) and 31 December 2013 (for the nine months period).

                (5) LTIFR =lost time injury frequency rate per one million hours worked; FIFR = fatal injury frequency rate per one million hours worked.

 

PRODUCTION BY MINE


3 months ended Dec 31,

% change1

(Y-o-Y)

3 months ended Sep 30,

 

% change1

(Q-o-Q)

12 months ended Dec 31,

% change1

(Y-o-Y)


2014

2013

2014

2014

2013










GOLD EQ. (KOZ) 2









Dukat operations

86

94

-8%

113

-24%

443

409

9%

Albazino-Amursk

51

68

-25%

62

-18%

227

238

-4%

Mayskoye

98

13

668%

42

134%

143

48

195%

Omolon operations

41

25

61%

69

-41%

226

158

43%

Voro

43

36

20%

42

2%

159

154

3%

Varvara

29

31

-5%

24

23%

106

131

-19%

Khakanja

43

44

-3%

37

17%

127

144

-12%

TOTAL

391

310

26%

388

1%

1,431

1,282

12%

Notes:     (1) % changes can be different from zero even when absolute numbers are unchanged because of rounding. Likewise, % changes can be equal to zero when absolute numbers differ due to the same reason. This note applies to all tables in this release.

                (2) Based on 1:60 Ag/Au and 5:1 Cu/Au conversion ratios.

CONFERENCE CALL AND WEBCAST

Polymetal will hold a conference call and webcast on Thursday, 29 January 17:30 Moscow time (14:30 London time).

To participate in the call, please dial:

8 10 8002 041 4011 access code 679755# (free from Russia), or

+44 (0) 20 3367 9454 (free from the UK), or

+1 855 402 7764 (free from the US), or

any of the above numbers (from outside the UK, the US and Russia) or follow the link:

http://www.audio-webcast.com/cgi-bin/visitors.ssp?fn=visitor&id=2515

Please be prepared to introduce yourself to the moderator or register.

Webcast replay will be available on Polymetal's website (www.polymetalinternational.com) and at http://www.audio-webcast.com/cgi-bin/visitors.ssp?fn=visitor&id=2515. A recording of the call will be available immediately after the call at +44 (0) 20 3367 9460 (from within the UK), +1 87 7642 3018 (from within the US) and +7 495 745 7948 (from within Russia), access code 291542#, from 6:30 pm Moscow time Thursday, January 29, till 6:30 pm Moscow time Thursday, February 5, 2015.

Enquiries

Media

 

Investor Relations

Instinctif Partners

Leonid Fink

Tony Friend

+44 20 7457 2020

Polymetal

Maxim Nazimok

Evgenia Onuschenko

 

ir@polymetalinternational.com

 

+7 812 313 5964 (Russia)

+44 20 7016 9503 (UK)

Joint Corporate Brokers

 

Morgan Stanley

Bill Hutchings

Sam McLennan

+44 20 7425 8000

RBC Europe Limited

Darrell Uden

Jonny Hardy

+44 20 7523 8350

FORWARD-LOOKING STATEMENTS

THIS RELEASE MAY INCLUDE STATEMENTS THAT ARE, OR MAY BE DEEMED TO BE, "FORWARD-LOOKING STATEMENTS". THESE FORWARD-LOOKING STATEMENTS SPEAK ONLY AS AT THE DATE OF THIS RELEASE. THESE FORWARD-LOOKING STATEMENTS CAN BE IDENTIFIED BY THE USE OF FORWARD-LOOKING TERMINOLOGY, INCLUDING THE WORDS "TARGETS", "BELIEVES", "EXPECTS", "AIMS", "INTENDS", "WILL", "MAY", "ANTICIPATES", "WOULD", "COULD" OR "SHOULD" OR SIMILAR EXPRESSIONS OR, IN EACH CASE THEIR NEGATIVE OR OTHER VARIATIONS OR BY DISCUSSION OF STRATEGIES, PLANS, OBJECTIVES, GOALS, FUTURE EVENTS OR INTENTIONS. THESE FORWARD-LOOKING STATEMENTS ALL INCLUDE MATTERS THAT ARE NOT HISTORICAL FACTS. BY THEIR NATURE, SUCH FORWARD-LOOKING STATEMENTS INVOLVE KNOWN AND UNKNOWN RISKS, UNCERTAINTIES AND OTHER IMPORTANT FACTORS BEYOND THE COMPANY'S CONTROL THAT COULD CAUSE THE ACTUAL RESULTS, PERFORMANCE OR ACHIEVEMENTS OF THE COMPANY TO BE MATERIALLY DIFFERENT FROM FUTURE RESULTS, PERFORMANCE OR ACHIEVEMENTS EXPRESSED OR IMPLIED BY SUCH FORWARD-LOOKING STATEMENTS. SUCH FORWARD-LOOKING STATEMENTS ARE BASED ON NUMEROUS ASSUMPTIONS REGARDING THE COMPANY'S PRESENT AND FUTURE BUSINESS STRATEGIES AND THE ENVIRONMENT IN WHICH THE COMPANY WILL OPERATE IN THE FUTURE. FORWARD-LOOKING STATEMENTS ARE NOT GUARANTEES OF FUTURE PERFORMANCE. THERE ARE MANY FACTORS THAT COULD CAUSE THE COMPANY'S ACTUAL RESULTS, PERFORMANCE OR ACHIEVEMENTS TO DIFFER MATERIALLY FROM THOSE EXPRESSED IN SUCH FORWARD-LOOKING STATEMENTS. THE COMPANY EXPRESSLY DISCLAIMS ANY OBLIGATION OR UNDERTAKING TO DISSEMINATE ANY UPDATES OR REVISIONS TO ANY FORWARD-LOOKING STATEMENTS CONTAINED HEREIN TO REFLECT ANY CHANGE IN THE COMPANY'S EXPECTATIONS WITH REGARD THERETO OR ANY CHANGE IN EVENTS, CONDITIONS OR CIRCUMSTANCES ON WHICH ANY SUCH STATEMENTS ARE BASED.

DUKAT OPERATIONS


3 months ended Dec 31,

% change

12 months ended Dec 31,

% change


2014

2013

2014

2013

MINING







Dukat







Underground development, m

8,354

7,302

+14%

31,204

30,717

+2%

Ore mined, Kt

392

308

+28%

1,468

1,253

+17%

Head grades







Gold, g/t




0.76

0.91

-16%

Silver, g/t




392

423

-7%








Goltsovoye







Underground development, m

1,617

1,873

-14%

6,742

7,102

-5%

Ore mined (underground), Kt

53

44

+21%

191

168

+14%

Silver head grade, g/t




624

624

-








Lunnoye + Arylakh







Waste mined, Kt

-

144

-100%

233

1,034

-78%

Underground development, m

953

1,540

-38%

4,876

6,612

-26%

Ore mined, Kt

89

85

+4%

384

394

-3%

Open-pit

-

12

-100%

36

86

-58%

Underground

89

73

+22%

348

308

+13%

Head grades







Open-pit







Gold, g/t




0.35

0.52

-33%

Silver, g/t




384

442

-13%

Underground







Gold, g/t




1.46

1.26

+16%

Silver, g/t




421

345

+22%








PROCESSING







Dukat







Ore processed, Kt

444

393

+13%

1,711

1,574

+9%

Head grades







Gold, g/t

0.38

0.72

-47%

0.66

0.73

-9%

Silver, g/t

315

425

-26%

406

425

-5%

Recovery1







Gold

79.7%

80.8%

-1%

85.4%

83.7%

+2%

Silver

83.4%

85.9%

-3%

86.5%

86.3%

+0%

Production







Gold, Koz

4.3

6.7

-36%

31.5

30.3

+4%

Silver, Moz

3.7

4.3

-13%

19.5

18.3

+7%

 

Lunnoye







Ore processed, Kt

102

81

+26%

400

338

+18%

Head grades







Gold, g/t

1.4

1.2

+18%

1.4

1.1

+21%

Silver, g/t

385

348

+11%

411

391

+5%

Recovery1







Gold

89.5%

86.3%

+4%

85.6%

85.6%

+0%

Silver

91.3%

89.7%

+2%

91.8%

89.3%

+3%

Production







Gold, Koz

3.7

2.5

+47%

13.9

10.2

+36%

Silver, Moz

1.0

0.8

+26%

4.4

3.8

+16%

TOTAL PRODUCTION







Gold, Koz

8.0

9.2

-13%

45.3

40.6

+12%

Silver, Moz

4.7

5.1

-7%

23.9

22.1

+8%

Note:       (1) Technological recovery, includes gold and silver within work-in-progress inventory (concentrate, precipitate).

At Dukat, silver production for the full year 2014 was 23.9 Moz, up 8% year-on-year, while gold production grew to 45.3 Koz, up 12% year-on-year, driven by a solid improvement in throughput and stable grades. Quarterly silver production at Dukat decreased to 4.7 Moz, a decrease of 7% year-on-year, which was driven by the planned decline in grade profile at the Dukat underground mine due to mine sequencing.

At Dukat, the amount of ore mined in Q4 and for the full year increased respectively by 28% and 17% year-on-year in line with the expanded processing capacity of the plant. At Goltsovoye, the amount of ore mined in Q4 increased 20% quarter-on-quarter and 21% year-on-year due to sustained improvements in dilution control and the reduction of mining losses.

The scheduled quarterly decrease in grades processed at the Omsukchan concentrator was partially offset by growth in plant throughput, which increased by 13% year-on-year to 444 Kt. The throughput increase was achieved as the plant was debottlenecked by shifting from three-stage to two-stage milling. Average recoveries during the quarter decreased slightly to 83.4% for silver and 79.7% for gold as a result of the scheduled decrease in grades.

At Arylakh, the underground development continued following the completion of open-pit mining in Q2. The ore is still predominantly sourced from Lunnoye underground mine with a variable grade profile driven by stope sequencing.

ALBAZINO-AMURSK 


3 months ended Dec 31,

% change

12 months ended Dec 31,

% change


2014

2013

2014

2013

MINING







Waste mined, Kt

4,243

3,494

+21%

16,321

16,135

+1%

Underground development, m

994

811

+23%

3,325

919

+262%

Ore mined (open pit), Kt

377

398

-5%

1,566

1,338

+17%

Gold head grade, g/t




4.9

5.5

-12%








PROCESSING







Albazino concentrator







Ore processed, Kt

395

406

-3%

1,609

1,513

+6%

Gold head grade, g/t

5.0

5.0

-0%

4.8

5.6

-13%

Gold recovery1

86.8%

88.5%

-2%

87.6%

88.2%

-1%

Concentrate produced, Kt

36.6

34.7

+5%

136.0

139.8

-3%

Concentrate gold grade, g/t

46.5

51.3

-9%

50.0

53.1

-6%

Gold in concentrate, Koz2

54.7

57.3

-4%

218.5

238.6

-8%

Concentrate sold, Kt

-

5.5

-100%

-

49.3

-100%

Payable gold in concentrate sold, Koz

-

9.4

-100%

-

79.1

-100%








Amursk POX







Concentrate processed, Kt

32.6

40.2

-19%

152.7

127.2

+20%

Gold head grade, g/t

48.3

50.1

-4%

50.1

49.8

+1%

Recovery

94.5%

93.0%

+2%

93.8%

86.0%

+9%

Gold produced, Koz

50.7

58.7

-14%

227.3

158.7

+43%

TOTAL PRODUCTION







Gold, Koz

50.7

68.0

-25%

227.3

237.7

-4%

Notes:     (1) To concentrate.

(2) For information only; not considered as gold produced and therefore not reflected in the table representing total production. Included in total production upon sale to off-taker.

At Albazino/Amursk, gold production in 2014 amounted to 227.3 Koz, down 4% year-on-year after de-stockpiling through sales to off-takers in 2013.

The amount of ore mined at Albazino open-pit in 2014 increased by 17% to 1,566 Kt, driven by the start of mining at the new Olga pit and commensurate with increased processing capacity.

Underground development originally excavated for exploration purposes will be used in 2015 to mine trial stopes to finalize the parameters of the future underground mine comprising Olga and Nadezhda zones.

Gold production at the POX plant in Q4 decreased by 18% quarter-on-quarter to 50.7 Koz as the POX plant went through a scheduled maintenance shutdown in October. Recoveries at the POX plant, at 94.5% in the quarter, exceeded the design level of 94%.

MAYSKOYE


3 months ended Dec 31,

% change

12 months ended Dec 31,


2014

2013

2014

2013

MINING







Underground development, m

2,395

2,357

+2%

10,536

9,989

+5%

Ore mined (underground), Kt

186

174

+7%

653

667

-2%

Gold head grade, g/t




8.4

7.4

+14%








PROCESSING







Ore processed, Kt

201

176

+15%

807

488

+66%

Gold head grade, g/t

8.1

7.8

+5%

8.7

7.1

+22%

Gold recovery1

86.7%

81.9%

+6%

83.6%

77.7%

+8%

Concentrate produced, Kt

21.5

19.6

+10%

92.7

48.7

+90%

Concentrate gold grade, g/t

66.2

57.3

+16%

63.1

55.3

+14%

Gold in concentrate, Koz2

45.8

36.1

+27%

188.1

86.6

+117%

Concentrate sold, Kt

50.1

7.6

+559%

72.4

30.3

+139%

Payable gold in concentrate sold, Koz

90.9

12.8

+610%

130.2

48.4

+169%








Amursk POX







Concentrate processed, Kt

6.4

0.02

NM3

9.9

0.02

NM 

Gold head grade, g/t

57.4

54.3

+6%

55.3

54.3

+2% 

Recovery

94.5%

-

NA4

92.2%

-

NA

Gold produced, Koz

7.5

-

NA

12.4

-

NA








TOTAL PRODUCTION







Gold, Koz

98.4

12.8

+668%

142.6

48.4

+195%

Notes:     (1) To concentrate.

(2) For information only; not considered as gold produced and therefore not reflected in the table representing total production. Included in total production upon sale to off-taker or internal downstream processing to saleable metal product.

(3) NM = not meaningful.

(4) NA = not applicable.

Total gold produced at Mayskoye during 2014 increased almost three-fold to 142.6 Koz. This was primarily driven by higher than average grades and increased processing volumes, as well as the commencement of concentrate processing at the Amursk POX plant and greater than two-fold increase of concentrate sales to China.

At the Mayskoye underground mine, underground development and the amount of ore mined increased by 5% in 2014 compared to 2013. The average grade processed in 2014 at the Mayskoye concentrator increased 22% year-on-year to 8.7 g/t bringing the 12 month average in line with the reserve average. This has also had a positive impact on recoveries at the concentrator, which were 86.7% in Q4.

Sales to off-takers in China peaked in October and November. During the quarter, the company sold 50 Kt of concentrate with the average grade of 63 g/t of gold, contributing 91 Koz of payable gold to the annual production. Total sales of concentrate in 2014 amounted to 130.2 Koz of payable gold.

Almost 10 Kt of concentrate was processed at the Amursk POX plant together with Albazino concentrate during 2014. In the fourth quarter the POX plant achieved above-design recoveries of 94.5% and contributed 7.5 Koz to total gold production from Mayskoye in Q4. The share of material processed at the Amursk POX compared to off-take sales is expected to be larger in 2015 as a sufficient amount of concentrate has now been delivered to the POX plant. The actual split will be determined on the basis of metallurgical properties of the material in order to optimise costs and recovery.

OMOLON OPERATIONS


3 months ended Dec 31,

% change

12 months ended Dec 31,

% change


2014

2013

2014

2013

MINING







Sopka







Waste mined, Kt

133

995

-87%

3,670

5,912

-38%

Ore mined (open pit), Kt

80

159

-50%

922

672

+37%

Head grades







Gold, g/t




4.6

3.9

+18%

Silver, g/t




175

142

+23%








Dalneye







Waste mined, Kt

1,230

1,986

-38%

2,385

3,695

-35%

Ore mined (open pit), Kt

335

268

+25%

550

584

-6%

Head grades







Gold, g/t




3.5

3.6

-3%

Silver, g/t




74

74

-








Tsokol







Waste mined, Kt

489

1,442

-66%

3,774

4,998

-25%

Ore mined (open pit), Kt

130

68

+91%

317

223

+42%

Gold head grade, g/t




4.3

4.8

-11%








Birkachan







Waste mined, Kt

-

-

NA

535

1,932

-72%

Underground development, m

649

-

NA

929

-

NA

Ore mined (open pit), Kt

-

-

NA

698

586

+19%

Gold head grade, g/t




2.6

1.8

+43%








TOTAL HUB







Waste mined, Kt

1,852

4,423

-58%

10,364

16,537

-37%

Ore mined , Kt

545

495

+10%

2,487

2,065

+20%








PROCESSING







Birkachan Heal Leach







Gold production, Koz

1.9

-

NA

6.0

-

NA








Kubaka Mill







Ore processed, Kt

215

217

-1%

825

767

+8%

Grade







Gold, g/t

4.6

4.0

+15%

6.7

5.1

+31%

Silver, g/t

44

8

+462%

133

118

+13%

Recovery1







Gold

93.7%

93.9%

-0%

94.7%

95.3%

-1%

Silver

78.8%

78.8%

+0%

83.5%

88.4%

-6%

Gold production, Koz

32.7

24.0

+36%

170.4

115.2

+48%

Silver production, Moz

0.4

0.1

+381%

2.9

2.6

+14%

TOTAL PRODUCTION







Gold, Koz

34.5

24.0

+44%

176.4

115.2

+53%

Silver, Moz

0.4

0.1

+390%

2.9

2.6

+15%

Note:       (1) Technological recovery, includes gold and silver within work-in-progress inventory.

At Omolon, gold and silver production increased by 53% and 15% year-on-year, respectively, driven by a higher grade profile, as well as an 8% increase in Kubaka mill throughput. In Q4, the Kubaka plant focused on processing Birkachan and Tsokol ores.

Open pit mining at Tsokol is nearing completion in Q2 2015 with underground development planned to commence in Q3 2015.

At Sopka, open-pit mining was completed in Q4 2014 with ore processing to be completed in Q3 2015. Potential for underground mining will be evaluated after the completion of detailed in-fill drilling campaign.

At Birkachan, open pit mining was completed in June, and the underground development started in Q3. Ore stoping is scheduled to start in Q4 2015. Open-pit mining at Oroch will start in Q2 2015. Ore from Oroch will be trucked by winter road starting from Q4 2015 for processing in 2016.

In 2015, processing will be split between Sopka, Birkachan, Dalnee and Tsokol with major volumes to be processed from Sopka and Birkachan.

At the Birkachan heap leach, irrigation of the existing leach pads continued in the quarter and 6 Koz of gold were recovered from the solution during twelve months 2014. There will be no additional ore stacking in 2015 as multi-year recoveries will continue to be monitored.

VORO


3 months ended Dec 31,

% change

12 months ended Dec 31,

% change


2014

2013

2014

2013

MINING







Voro







Waste mined, Kt

2,881

2,745

+5%

11,030

11,099

-1%

Ore mined (open pit), Kt

296

347

-15%

1,893

1,787

+6%

-     primary

221

205

+7%

935

807

+16%

-     oxidised

76

141

-46%

958

981

-2%

Gold head grades







-     primary, g/t




5.2

5.7

-8%

-     oxidized, g/t




1.8

1.5

+17%








PROCESSING







Voro Heap Leach







Ore stacked, Kt

60

164

-63%

747

850

-12%

Gold head grade, g/t

1.3

1.2

+8%

1.4

1.4

+6%

Gold recovery

74.4%

72.9%

+2%

74.2%

73.7%

+1%

Gold production, Koz

9.2

8.0

+15%

27.7

23.5

+18%

Voro CIP







Ore processed, Kt

219

230

-5%

915

924

-1%

Gold head grade, g/t

5.2

5.0

+5%

5.6

5.7

-1%

Gold recovery

78.8%

79.7%

-1%

82.5%

79.9%

+3%

Gold production, Koz

33.0

27.4

+20%

129.8

129.2

+0%

TOTAL PRODUCTION







Gold, Koz1

42.2

35.4

+19%

157.5

152.7

+3%

Silver, Moz

0.030

0.014

+115%

0.101

0.079

+27%

Note:       (1) Including the effect of rounding

Gold production at Voro in 2014 increased slightly by 3% year-on-year to 157.5 Koz as higher recoveries at CIP plant offset lower grades.

Ore mined during 2014 was 6% higher year-on-year, with the majority of the increase attributable to primary ore.

Ore stacking at the heap leach plant will be nearing completion in 2015, with the 400-450 Kt of ore to be stacked during the year. Processing at the CIP plant will continue at a steady pace. Near-mine exploration continues to focus on the potential sources of heap leachable mineralisation.

 

VARVARA


3 months ended Dec 31,

% change

12 months ended Dec 31,

% change


2014

2013

2014

2013

MINING







Waste mined, Kt

6,759

7,883

-14%

30,552

31,053

-2%

Ore mined (open pit), Kt

1,295

558

+132%

3,985

2,008

+98%

 - float ore




750

499

+50%

 - leach ore




3,235

1,510

+114%

Head grades







 - gold, float ore, g/t




1.4

1.3

+6%

 - copper, float ore, %




0.45%

0.64%

-30%

 - gold, leach ore, g/t




1.2

1.2

-3%








PROCESSING







Flotation







Ore processed, Kt

-

244

-100%

547

1,005

-46%

Grade

-






Gold, g/t

-

1.4

-100%

1.1

1.3

-10%

Copper

-

0.39%

-100%

0.40%

0.58%

-31%

Recovery1







Gold

-

52.9%

-100%

47.3%

56.2%

-16%

Copper

-

81.5%

-100%

80.7%

88.5%

-9%

Production







Gold (in concentrate), Koz

-

5.2

-100%

7.8

21.1

-63%

Copper (in concentrate), t

-

749

-100%

1,631

4,841

-66%

Leaching







Ore processed, Kt

976

662

+47%

3,117

2,671

+17%

Gold head grade, g/t

1.1

1.3

-10%

1.1

1.3

-10%

Gold recovery1

81.1%

80.0%

+1%

77.7%

81.7%

-5%

Gold production (in dore), Koz

29.4

22.0

+34%

90.3

85.7

+5%

TOTAL PRODUCTION







Gold, Koz

29.4

27.2

+8%

98.0

106.8

-8%

Copper, t

-

749

-100%

1,631

4,841

-66%

Note:       (1) Technological recovery, includes gold and copper within work-in-progress inventory.

At Varvara, gold and copper production in 2014 declined by 8% and 66% respectively as a result of a temporary suspension of the flotation circuit in July in order to prevent accumulation of excess concentrate stockpiles in a weaker copper concentrate market. Mining was re-directed and focused on the gold ore. As a result of further deterioration in copper price in the beginning of 2015, re-start of the copper circuit is likely to be delayed till 2016.

In Q4, the amount of ore mined increased by 10% quarter-on-quarter and more than two-fold year-on year as the mine has switched to mining ore at the South pit. The total amount of ore mined in 2014 increased by 98% from the previous year.

Recoveries dropped to 78% in Q3 as leaching time decreased on the back of throughput expansion at the leaching circuit. As several metallurgical initiatives were implemented, gold recoveries increased to 81% in Q4 with further improvements expected in 2015.

 

KHAKANJA


3 months ended Dec 31,

% change

12 months ended Dec 31,

% change


2014

2013

2014

2013

MINING







Khakanja + Yurievskoye







Waste mined, Kt

1,140

922

+24%

4,671

3,096

+51%

Ore mined, Kt

94

-

NA

271

294

-8%

Open-pit

94

-

NA

271

290

-6%

Underground

-

-

NA

-

5

-100%

Head grades







Open-pit







Gold, g/t




3.0

1.4

+106%

Silver, g/t




142

143

-1%

Underground







Gold, g/t




-

7.9

-100%

Silver, g/t




-

12

-100%








Avlayakan







Waste mined, Kt

-

178

-100%

-

1,287

-100%

Underground development, m

870

811

+7%

3,805

919

+314%

Ore mined, Kt

24

21

+12%

42

84

-50%

Open-pit

-

19

-100%

-

81

-100%

Underground

24

3

+811%

42

3

NM

Head grades







Open-pit







Gold, g/t




-

9.1

-100%

Silver, g/t




-

122

-100%

Underground







Gold, g/t




13.8

3.6

+284%

Silver, g/t




105

18

+498%








Ozerny







Waste mined, Kt

789

1,239

-36%

4,288

4,714

-9%

Ore mined (open pit), Kt

341

153

+123%

764

319

+139%

Head grades







Gold, g/t




4.0

3.6

+12%

Silver, g/t




28

40

-29%








TOTAL HUB







Ore mined, Kt

459

174

+164%

1,077

697

+54%








PROCESSING







Ore processed, Kt

159

156

+2%

622

619

+1%

Grade







Gold, g/t

7.7

8.2

-6%

5.3

5.7

-7%

Silver, g/t

108

116

-7%

117

147

-20%

Recovery1







Gold

96.0%

87.3%

+10%

93.9%

92.3%

+2%

Silver

71.7%

84.6%

-15%

74.3%

84.2%

-12%

TOTAL PRODUCTION







Gold, Koz

36.4

35.7

+2%

97.9

103.4

-5%

Silver, Moz

0.4

0.5

-22%

1.7

2.4

-29%

Note:       (1) Technological recovery, includes gold and silver within work-in-progress inventory (precipitate)

Gold production at Khakanja in 2014 decreased 5% year-on-year to 97.9 Koz, while silver production was 1.7 Moz, down 29% year-on-year. These decreases were driven by planned grade declines as the Khakanja mine is nearing depletion and the mill feed is complemented by material from lower-grade stockpiles.

Quarter-on-quarter gold production increased by 2% as the Company was processing high-grade material from Avlayakan mine. Quarterly silver production decreased by 22% as significant amounts of feedstock came from stockpiles with lower recovery rates.

In Q4 mining at Ozerny increased 4 times to 341 Kt quarter-on-quarter, ahead of winter road operating season. At Ozerny and Khakanja, open pit mining will be completed in 2015 in Q1 and Q2 respectively with mining fleet to be re-directed to Svetloye.

In 2014 the Company completed all preparatory works at Svetloye ahead of construction in 2015. Sea-side access point and all-season road from the shore to the site have been fully established. Mining is expected to start in Q4 2015.

KYZYL

Pilot metallurgical testing of the Kyzyl ore has confirmed the viability of ore flotation to concentrate and signals the potential to improve the parameters achieved in previous test work.

Decommissioning of old infrastructure, site clearing, and various permitting activities, including ESIA preparation, have continued as planned. Preliminary public consultations with the Bakyrchik community have been successfully completed.

Polymetal is on track to publish the full feasibility study for the project in Q4 2015 and start full-scale construction in Q2 2016.

HEALTH AND SAFETY

Polymetal regrettably reports the loss of three colleagues during the calendar year 2014. There was also one workplace fatality at a contractor's operation.

The increased fatality rate is currently a major area of focus at both the Board and at the executive management level. The analysis performed shows that the decline in safety performance was partially attributable to the increased scope of underground mining at our operations in complex geotechnical conditions.

The Company intends to significantly reduce risks and improve health and safety performance by employees of the Company and our contractors during the year ahead aiming for zero fatalities in 2015. The Company has already launched new risk assessment systems and started the implementation of additional measures to ensure proper enforcement of existing safety standards and management procedures. We are also taking further actions to extend and refine personal safety and risk awareness across our operating mines.

PERSONNEL

Aleksandr Simon (41), former Managing Director of Albazino, was appointed Director General of Varvara. Mr. Simon joined Polymetal in 2003 as a Deputy Managing Director for Production at Lunnoye and then served as Managing Director. Starting from 2008, Mr. Simon worked as a Chief Engineer and then as an Executive and Managing Director of Albazino. Mr. Simon graduated from St. Petersburg Mining Institute majoring in open pit mining.

Aleksey Sharabarin (41) was appointed Managing Director of Albazino. Mr. Sharabarin joined Polymetal in 2006 as drilling-and-blasting section superintendent at Voro and then worked as a Chief Engineer at Dukat, and later, starting from 2011, worked as a Chief Engineer at Albazino. Mr. Sharabarin graduated from Krasnoyarsk State Academy of Precious Metals and Gold majoring in open pit mining. In 2006, he underwent professional retraining in the International Management Institute LINK on the management program.

 

Polymetal has published an updated Company presentation today. A copy of the presentation is available on the Company's website at: http://www.polymetalinternational.com/investors-and-media/presentations-webcasts/presentations/2015.aspx?sc_lang=en

 


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCKMGZMVLFGKZG

Top of Page