RNS Number : 3741M
Hochschild Mining PLC
20 January 2016
 

 

 

20 January 2016  

 

 

Production Report for the 12 months ended 31 December 2015

 

 

Strong 2015 operational delivery

§ Full year production of 24.7 million attributable silver equivalent ounces exceeding 24.0 million target1

14.8 million ounces of silver

166.0 thousand ounces of gold

27.0 million silver equivalent ounces using 2015 average gold/silver ratio

§ Inmaculada mine produced 7.1 million silver equivalent ounces exceeding 6-7 million ounce forecast1

84.6 thousand ounces of gold

2.1 million ounces of silver

8.3 million silver equivalent ounces using 2015 average gold/silver ratio

§ 2015 all-in sustaining costs per silver equivalent ounce on track to meet $13-14 guidance

 

Improved financial position

§ $100 million equity rights issue completed

§ $105 million of debt repaid in Q4

§ Total cash of approximately $83 million as at 31 December 2015

§ Net debt of approximately $366 million as at 31 December 2015

§ Argentina macroeconomic & tax reforms expected to significantly improve San Jose cash flows

§ Cashflow further strengthened by 2016 precious metal hedges:

71,000 ounces of gold at $1,154 per ounce

29,000 ounces of gold at $1,145 per ounce

6.0 million ounces of silver at $15.93 per ounce

 

2016 guidance

§ Attributable production target of 32.0 million silver equivalent ounces

§ All-in sustaining costs expected to be $12-13 per silver equivalent ounce

Inmaculada costs expected to be $9-10 per silver equivalent ounce

§ Total sustaining and development capital expenditure expected to be approximately $100 million including $10 million to develop Pablo vein

§ Pablo vein preliminary economics indicate:

NAV of $25-50 million

All in sustaining costs to average $10-11 per silver equivalent ounce

 

 

_____________________

1 Calculated using the previous Company gold/silver ratio of 60x. All other equivalent figures assume the average gold/silver ratio for 2015 of 74x.

 

 

Ignacio Bustamante, Chief Executive Officer commented:

"The operational performance during 2015 exceeded expectations as we once again beat our annual production target and are maintaining our guidance on full year costs. The mines delivered a very solid fourth quarter with our new low cost Inmaculada mine performing particularly strongly. We are building on this positive momentum by focusing on delivering low cost production from Pablo which we expect will further demonstrate our brownfield potential and ability to deliver strong cash flow generation from our existing assets. In addition, the recent regulatory and economic policy changes in Argentina offer a promising future for our high grade San Jose mine which, supported by the solid operational performance, is now in a good position to improve its cashflow contribution.

 

We have also made substantial progress in strengthening our balance sheet through our own cash generation and the rights issue completed in the fourth quarter of last year. Following large debt repayments in the period, we have ended the year with net debt reduced by approximately 20% versus the half year position. The maturities of the bulk of the remaining debt are also adequately profiled.

 

We enter 2016 with a renewed sense of excitement: a fourth consecutive year of production increases and reduced costs; a low risk organic project; a stronger balance sheet; and several brownfield exploration targets with the potential to continue improving the quality and quantity of our existing resources."

__________________________________________________________________________________

 

A conference call will be held at 2.30pm (London time) on Wednesday 20 January 2016 for analysts and investors. 

Dial in details as follows:

International Dial in:    +44 (0) 20 3139 4830

UK Toll-Free Number: +44(0) 808 237 0030

Pin: 47755168#

 

A recording of the conference call will be available for one week following its conclusion, accessible from the following telephone number:

International: +44 (0) 20 3426 2807

UK Toll Free: +44(0) 808 237 0026

Pin: 666619#

__________________________________________________________________________________

 

 

Note: silver/gold equivalent production figures assume the average gold/silver ratio for 2015 of 74:1.

 

Overview

In Q4 2015, the Company delivered attributable production of 9.4 million silver equivalent ounces, comprised of 4.3 million ounces of silver and 68.4 thousand ounces of gold. This has brought the total for 2015 to 27.0 million silver equivalent ounces (24.7 million ounces using the Company's previous gold/silver ratio of 60:1), comprising 14.8 million ounces of silver and 166 thousand ounces of gold.

 

The Company reiterates that its all-in sustaining costs per silver equivalent ounce for 2015 is expected to be between $13 and $14.

 

Production

Inmaculada

Following a successful ramp-up in the third quarter, total silver equivalent production in Q4 at Inmaculada reached 4.4 million silver equivalent ounces consisting of 45.1 thousand ounces of gold and 1.1 million ounces of silver, driven by consistent gold and silver grades and increased tonnage as the processing plant operated at closer to 3,850 tonnes per day in the period.

 

Production therefore in 2015 slightly improved on the targeted range, coming in at 8.3 million silver equivalent ounces consisting of 84.6 thousand ounces of gold and 2.1 million ounces of silver.

 

Arcata

At Arcata, total silver equivalent production in Q4 was 1.8 million ounces (Q4 2014: 1.9 million ounces) which brought the year-to-date total to 6.8 million ounces (2014: 7.1 million ounces). Despite introducing an adjusted mine plan at the start of 2015 to ensure the extraction of profitable ounces, Arcata has delivered a much stronger year than expected. A successful brownfield exploration programme has ensured considerable tonnage at higher silver grades than expected.

 

Pallancata

At Pallancata, tonnage in the fourth quarter was lower due to ongoing effects of the above-mentioned adjusted mine plans resulting in production of 1.1 million silver equivalent ounces (Q4 2014: 2.0 million ounces), although grades continued to be consistent. The total for the year, at 4.9 million silver equivalent ounces (2014: 8.3 million ounces), reflects the adjusted mining plan with the Selene plant expected to transition to the new Pablo vein later in 2016. See further details of the Pablo vein below.  

 

San Jose

The San Jose operation once again delivered a strong fourth quarter, as expected, with rising tonnage and strong grades, delivering 4.2 million silver equivalent ounces (Q4 2014: 4.0 million ounces). For the whole of 2015, the operation produced a record 13.9 million silver equivalent ounces (2014: 13.4 million ounces) driven by better than projected silver and gold grades.

 

On 17 December 2015, the Argentinean peso fell by approximately 40% against the dollar following the decision by the government to lift capital controls. With approximately 70% of operating costs at San Jose incurred in pesos, the effect of this significant devaluation is already having a material impact on the mine's cost position.

 

The Argentinean government published a decree on 2 November 2015 restoring the right to receive a rebate from goods exported through Patagonian ports (previously cancelled in 2009). This benefit is applicable to Hochschild at a rate of approximately 9% of the FOB value of its exports which amounts to approximately $15 million per annum. The current estimate for collection is approximately two years.

 

In late December 2015, following an announcement by the new government that they would remove export taxes on agricultural and industrial products, it was subsequently confirmed that the decree included removal of the 5% export tax on finished mining products such as dore (approximately 50% of the mine's output). Along with the above-mentioned recent elimination of exchange controls and import restrictions within the country as well as the resulting devaluation of the peso, the Company expects overall economic and operating environment in Argentina to improve significantly.

 

Average realisable prices and sales

Average realisable precious metal prices in Q4 2015 (which are reported before the deduction of commercial discounts and include the effects of the existing hedging agreements) were $1,116/ounce for gold and $15.0/ounce for silver (Q4 2014: $1,222/ounce for gold and $17.1/ounce for silver).

 

For 2015 as a whole, average realisable precious metal prices were $1,159/ounce for gold and 16.0/ounce for silver (2014: $1,279/ounce for gold and $18.9/ounce for silver).

 

 

 

Brownfield exploration2

Arcata

In Q4 2015, 5,956 metres were drilled in the Stephani, Macarena, Tunel 3 & Tunel 4 veins. Some highlights are presented below:

 

Vein

Results

Tunel 3

DDH871-GE15:1.2m @1.04 g/t Au & 1,135 g/t Ag

DDH872-GE15:1.3m @2.09 g/t Au & 1,196 g/t Ag

Tunel 4

DDH878-GE15:1.0m @ 2.4 g/t Au & 3,479 g/t Ag

DDH883-GE15:1.7m @ 1.6 g/t Au & 1,729 g/t Ag

 

Pallancata

Following the initial discovery of the Pablo vein during the third quarter, drilling has continued and an initial inferred resource has been achieved. The Company's preliminary economics for a two year mine life for the Pablo vein are detailed below. Resources (unaudited) are estimates based on a cut-off grade of 103g/t silver equivalent.

 

Pablo

 

Inferred resources (kt) (unaudited)

1,251

Ag grade (g/t)

344

Au grade (g/t)

1.3

LOM production (M oz Ag Eq)

12.6

LOM AISC ($/oz Ag Eq)

10.6

 

LOM Cashflows ($m)

 

Revenue

161.4

Costs

(108.5)

Selling expenses 

(3.0)

Capital expenditure

(19.7)

Taxes (SMT & Royalties)

(2.4)

Pre-tax total

27.9

NAV @5% (spot metal prices)

24.3

NAV @5% (analyst consensus prices)

51.8

Spot metal prices: $14/oz Ag; $1,100/oz Au

Analyst Consensus: $17/oz Ag; $1,196/oz Au

 

Work has started on mine development to access the vein and the Company currently expects to have initial production from Pablo towards the end of 2016.

 

Drilling has continued at the deposit and 7,242 metres were drilled at Pablo and Yurika veins during the quarter. Preliminary results are below:

 

Vein

Results

Pablo

DLEP-A21: 9.0m @0.68 g/t Au & 225 g/t Ag

DLEP-A23: 7.1m @1.09 g/t Au & 389 g/t Ag

DLEP-A24: 2.9m @1.34 g/t Au & 334 g/t Ag

DLEP-A25: 9.0m @1.20 g/t Au & 324 g/t Ag

DLEP-A26: 4.7m @0.73 g/t Au & 290 g/t Ag

Yurika

DLYU-A97: 2.8m @1.66 g/t Au & 438 g/t Ag

Yurika ceiling

DLYU-A97: 1.5m @ 3.94 g/t Au & 748 g/t Ag

DLYU-A99: 1.0m @ 0.89 g/t Au & 231 g/t Ag

 

 

Financial position

During the period the Company repaid $105 million of debt financed from the proceeds of the rights issue completed on 4 November 2015 and existing cash resources. $50 million of the $100 million Scotiabank medium term loan was repaid with the remaining balance to now amortise on a quarterly basis in 2018 and 2019, representing a maturity extension from the original terms at the same interest rate. In addition, $55 million of the $350 million Senior Notes due 2021 have been repurchased at a discount to par and have been subsequently cancelled.

 

Furthermore, the terms of $25 million of short term debt due December 2015 have been renegotiated such that this tranche of debt has been rolled over for a further year at an interest rate of 1.35% per annum.

 

Following this debt repayment programme, total cash was approximately $83 million as at 31 December 2015, resulting in net debt of approximately $366 million.

 

On 6 October 2015, the Company signed agreements to hedge the sale of 29,000 ounces of gold at $1,145 per ounce and 6.0 million ounces of silver at $15.93 per ounce for 2016. This is in addition to a previous agreement for 2016 to hedge the sale of 71,000 ounces of gold at a price of $1,154 per ounce.

 

____________________

2 Please note that in line with industry-wide standards, all mineralised intersections in this release are quoted as calculated true widths.

 

Outlook

The overall production target for 2016 is 32.0 million silver equivalent ounces, assuming the average silver-to-gold ratio for 2015, which consists of just over 14 million ounces from Inmaculada, approximately 7 million attributable ounces from the 51% owned San Jose and the balance from the remaining two Peruvian operations.

 

The all-in sustaining cost per silver equivalent ounces in 2016 is expected to be between $12 and $13 (projected assuming the average silver-to-gold ratio for 2015) with Inmaculada costs forecast to be between $9 and $10 per ounce and San Jose at approximately $13 per ounce with the remaining Peruvian mines at approximately $14.5 per ounce.

 

The overall capital expenditure budget for 2016 is approximately $100 million allocated to sustaining and development expenditure. This consists of: approximately $35 million at Inmaculada; $10 million to develop the Pablo vein structure; $23 million at Arcata; and the balance of $30 million at the San Jose operation.

 

__________________________________________________________________________________

 

Enquiries:

 

Hochschild Mining plc

Charles Gordon                                                                                                                                               +44 (0)20 3714 9040

Head of Investor Relations

 

Hudson Sandler

Charlie Jack                                                                                                                                                     +44 (0)207 796 4133

Public Relations

__________________________________________________________________________________

 

 

About Hochschild Mining plc

Hochschild Mining plc is a leading precious metals company listed on the London Stock Exchange (HOCM.L / HOC LN) with a primary focus on the exploration, mining, processing and sale of silver and gold. Hochschild has over fifty years' experience in the mining of precious metal epithermal vein deposits and currently operates four underground epithermal vein mines, three located in southern Peru and one in southern Argentina. Hochschild also has numerous long-term projects throughout the Americas.

 

 

 

 

PRODUCTION & SALES INFORMATION*

 

TOTAL GROUP PRODUCTION

Total production includes 100% of all production, including production attributable to Hochschild's joint venture partner at San Jose.

 

ATTRIBUTABLE GROUP PRODUCTION

 

Q4 
2015

Q3 
2015

 Q4               2014

12 mths 
2015

12 mths                        2014

Silver production (koz)

4,345

4,142

4,115

14,752

16,187

Gold production (koz)

68.44

56.97

24.38

166.02

100.89

Silver equivalent (koz)

9,410

8,358

5,919

27,037

23,653

Silver equivalent (koz) (60:1)

8,452

7,560

5,578

24,713

22,241

Gold equivalent (koz)

127.16

112.94

79.99

365.37

319.64

Gold equivalent (koz) (60:1)

140.86

126.00

92.96

411.88

370.68

Attributable production includes 100% of all production from Arcata, Pallancata and Ares and 51% from San Jose.

 

QUARTERLY PRODUCTION BY MINE

 

ARCATA

Product

Q4 
2015

Q3 
2015

 Q4               2014

12 mths 
2015

12 mths                        2014

Ore production (tonnes treated)

184,994

162,133

186,486

648,051

701,947

Average grade silver (g/t)

288

331

307

323

286

Average grade gold (g/t)

1.03

0.99

0.90

0.99

0.85

Silver produced (koz)

       1,453

       1,434

       1,579

5,613

5,827

Gold produced (koz)

4.58

3.92

4.40

15.67

16.89

Silver equivalent (koz)

       1,792

1,725

       1,904

6,772

             7,077

Silver equivalent (koz) (60:1)

1,728

1,670

1,843

6,553

6,841

Silver sold (koz)

1,798

1,172

1,550

5,653

5,621

Gold sold (koz)

5.30

3.07

4.06

15.29

15.66

 

 

ARES

Product

Q4 
2015

Q3 
2015

 Q4               2014

12 mths 
2015

12 mths                        2014

Ore production (tonnes treated)

-

-

-

-

167,331

Average grade silver (g/t)

-

-

-

-

110

Average grade gold (g/t)

-

-

-

-

2.34

Silver produced (koz)

-

-

-

-

534

Gold produced (koz)

-

-

-

-

             11.63

Silver equivalent (koz)

-

-

-

-

             1,395

Silver equivalent (koz) (60:1)

-

-

-

-

1,232

Silver sold (koz)

-

-

17

-

540

Gold sold (koz)

-

-

-

-

11.45

INMACULADA

Product

Q4 
2015

Q3 
2015

 Q4               2014

12 mths 
2015

12 mths                        2014

Ore production (tonnes treated)

329,925

277,486

-

659,737

-

Average grade silver (g/t)

118

116

-

115

-

Average grade gold (g/t)

4.57

4.39

-

4.36

-

Silver produced (koz)

1,084

875

-

2,055

-

Gold produced (koz)

       45.11

       36.12

-

             84.64

-

Silver equivalent (koz)

       4,423

       3,547

-

8,318

-

Silver equivalent (koz) (60:1)

3,791

3,042

-

7,133

-

Silver sold (koz)

1,546

92

-

1,638

-

Gold sold (koz)

63.87

3.64

-

67.51

-

 

 

 

PALLANCATA

Product

Q4 
2015

Q3 
2015

 Q4               2014

12 mths 
2015

12 mths                        2014

Ore production (tonnes treated)

107,320

125,560

256,299

522,431

1,051,068

Average grade silver (g/t)

          272

          272

          224

259

238

Average grade gold (g/t)

1.40

1.36

1.00

1.28

1.03

Silver produced (koz)

          791

925

       1,537

3,664

6,527

Gold produced (koz)

3.74

4.23

6.09

16.42

24.34

Silver equivalent (koz)

       1,068

       1,238

       1,988

4,879

             8,329

Silver equivalent (koz) (60:1)

1,016

1,179

1,902

4,649

7,988

Silver sold (koz)

918

729

1,506

3,632

6,502

Gold sold (koz)

4.27

3.20

5.80

15.80

24.02

. 

 

 

SAN JOSE

Product

Q4 
2015

Q3 
2015

 Q4               2014

12 mths 
2015

12 mths                        2014

Ore production (tonnes treated)

154,642

144,851

152,689

532,488

571,017

Average grade silver (g/t)

453

441

454

448

404

Average grade gold (g/t)

6.63

6.09

6.19

6.36

5.77

Silver produced (koz)

1,994

1,780

1,959

6,706

6,469

Gold produced (koz)

29.44

24.90

27.23

96.64

94.16

Silver equivalent (koz)

       4,172

       3,623

       3,974

13,857

           13,437

Silver equivalent (koz) (60:1)

3,760

3,274

3,593

12,504

12,119

Silver sold (koz)

1,604

1,620

2,163

6,340

6,316

Gold sold (koz)

23.17

22.87

30.13

88.79

91.28

 The Company has a 51% interest in San Jose.

 

*Silver equivalent production assumes the average gold/silver ratio for 2015 of 74:1 unless otherwise stated.

 

Forward looking statements

This announcement may contain forward looking statements. By their nature, forward looking statements involve risks and uncertainties because they relate to events and depend on circumstances that will or may occur in the future. Actual results, performance or achievements of Hochschild Mining plc may, for various reasons, be materially different from any future results, performance or achievements expressed or implied by such forward looking statements.

 

The forward looking statements reflect knowledge and information available at the date of preparation of this announcement. Except as required by the Listing Rules and applicable law, the Board of Hochschild Mining plc does not undertake any obligation to update or change any forward looking statements to reflect events occurring after the date of this announcement. Nothing in this announcement should be construed as a profit forecast.

- ends -